August will see the beginning of mainline pipeline construction that’s expected to continue through 2021 and employ over 2,000 individuals primarily through our prime contractors. Four different groups will execute this task along the pipeline right-of-way, each focused on one or two of Coastal GasLink’s eight sections.
“Mainline pipe installation is like a moving assembly line. Once the land is cleared and graded, crews can line up pipe sections roughly 20 m in length along the route to bend, weld and coat. Then, pipe is lowered into the ground and covered. The entire process for placing segments of pipe can happen over a few days to weeks, including backfilling the trench,” says Dan.
“There’s no question this is an exciting development of the project, but just as important is the continued health and safety of our workers and stakeholders, focus on our communities and Indigenous partners, and consideration for the environment,” says Dan.