Coastal GasLink reaches 75% overall completion, positioning Project for a strong finish to 2022
This September, construction of Coastal GasLink reached 75 per cent completion overall, with a number of milestone completions and major advancements well underway. Favourable weather conditions over the summer enabled crews to begin pipe installation at Cable Crane Hill, a steep slope in the Coast Mountains, resulting in 30 per cent of pipe being installed ahead of schedule. Nearby, crews used a raised bore technique to tunnel through a mountain at Steep Slope 3. This incredible feat of engineering is enabling increased safety and efficiency, including overall cost and schedule improvements. On the eastern end of the Project, crews are making significant progress along steep slopes at Mount Merrick and the Headwall.
Nearly all major watercourse crossings complete
Our dedicated construction and environment teams are working together to ensure we are protecting and caring for critical waterways across the 670-kilometre project route. With the recent completion of the Crocker Creek Direct Pipe Installation (DPI) in Section 3, we have now safely and successfully completed 9 out of 10 major watercourse crossings. To learn more about how we protect this valuable resource, visit our website: Coastal GasLink – Water crossings
Reclamation advancing across right-of-way
Reclamation is the final stage of pipeline construction and involves restoring the environment back to its preconstruction state. And in some cases, such as the former Vanderhoof lodge site which is now complete, we worked together with the District of Vanderhoof and agricultural consultants to restore and enhance agricultural viability of this site.
Read our full October construction update.
Photo of the month